Srinath, N. R.
N. R. Srinath has more than 14 yr of experience in the design and engineering of heat transfer equipment in the energy and chemical sectors. He began his career with Foster Wheeler India in 2007 and has worked at Fluor New Delhi since 2013.
Case study: Challenges in the selection of a helical baffled exchanger
In a greenfield project, a proprietary heat exchanger<sup>a</sup> has been found to be preferable to conventional shell-and-tube (S&T) exchangers to optimize the total lifecycle cost (i.e., capital, operating, installation and maintenance costs).
- 1
- ... 1 pages
Current Digital Edition
Sign up to Receive Our Newsletter
Latest News
- NextChem Tech selected as engineering and technology partner for Aliplast’s upcycling plant project in Italy 3/29
- Russia's Ryazan oil refinery restores crude processing to 60% of pre-attack level 3/28
- Global refinery capacity totaling 3.6 MM bpd at high-risk of closure 3/28
- More than 20% of global oil refining capacity at risk, analysis finds 3/28
- SABIC Fujian Petrochemicals advances major ethylene project with Lummus technologies and services 3/28
- Singapore fuel oil stockpiles slip to two-week low 3/28
Construction Boxscore: Project Spotlight
Project:
Long Son Petrochemicals Complex
Location:
Long Son, Vietnam
Operator:
Siam Cement Group
Cost:
$5.4 B
Capacity:
1.65 MMtpy
Completion date:
2023
Status:
Under Construction